Proud to share the successful completion of the Primark Refit at The Centre, Livingston — delivered over a focused 9-week programme.
Key elements of the project included:
• Till bank upgrades across both the first and ground floors, along with the installation of 18 new self check out units
• Mid-floor wall installations on both levels
• Full replacement of perimeter panels and columns
• Back of house flooring and decoration works now complete
• New Back of house furniture installed
• Atrium wall fully overhauled with fresh vinyl and updated graphics
A huge well done to all of the IDC team and subcontractors for ensuring another successful delivery within a live retail environment.
One of our final major completions of the year — a strong finish to an incredibly productive period.